5/30/2019 - Revised Milling/Paving Schedule, Southern Connecticut Gas Main Replacement Program

May 30, 2019 - Gas Main Installation, Spring 2019

Milling starts Monday, June 3 for 8 to 9 days (weather permitting).

Paving starts Tuesday, June 4 or Wednesday, June 5 for 11 to 12 days (weather permitting).

DATE L W STREET SQ YD TONS SY
Town's Half
Monday,
June 3
411 28 Crescent Street 1,279 110 639
1,530 29 Catherine Terrace 4,930 425 2,465
700 30 Catherine Street 2,333 201 1,167
687 28 Ann Street 2,137 184 1,069
10,679
Tuesday,
June 4
700 30 Hurd Street 2,333 201 1,167
330 19 Narrow Street 697 60 348
340 28 Sommerville Street 1,058 91 529
808 26 Gould Ave 2,334 201 1,167
370 31 Mellow Street 1,274 110 637
385 29 Hollis Street 1,241 107 620
390 29 Carlton Street 1,257 108 628
10,194
Wednesday,
June 5
344 30 Sullivan Place 1,147 99 573
1,024 31 Mona Terrace 3,527 304 1,764
966 28 Oldfield Drive 3,005 259 1,503
1,560 25 Eastlawn Street 4,333 374 2,167
12,012
Thursday,
June 6
1,017 29 Smith Street 3,277 283 1,639
593 28 Dwight Street 1,845 159 922
254 30 Paulding Street (Millard to Dwight) 847 73 423
1,485 30 Millard Street 4,950 427 2,475
366 29 Lind Street 1,179 102 590
12,098
Friday,
June 7
1,205 29 Longdean Road 3,883 335 1,941
972 29 Forest Avenue 3,132 270 1,566
605 31 Cummings Avenue 2,084 180 1,042
165 29 Whetsone Hill Court 532 46 266
169 27 Reef Court 507 44 254
10,137
Monday,
June 10
764 28 Charles Street 2,377 205 1,188
800 30 Howard Street 2,667 230 1,333
1,557 30 Pratt Street 5,190 447 2,595
10,234
Tuesday,
June 11
1,905 20 Veres Street 4,233 365 2,117
170 43 Sandy Way 812 70 406
903 30 Quincy Street (Reef - Rowland, 2 sections) 3,010 259 1,505
426 28 Jarvis Court 1,325 114 663
945 30 Fox Street 3,150 272 1,575
12,531
Wed. June 12 486 29 Edward Street (Rowland to Lalley) 1,566 135 783
2,789 27 Lalley Boulevard 8,367 721 4,184
9,933
Reclaim
June 13
1,210 30 Blaine Street 4,033 812 2,017
91,851 8,383 45,926